Canada Gazette, Part I, Volume 150, Number 12: National Energy Board Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies
March 19, 2016
Statutory authority
National Energy Board Act
Sponsoring agency
National Energy Board
REGULATORY IMPACT ANALYSIS STATEMENT
For the Regulatory Impact Analysis Statement, see the National Energy Board Pipeline Damage Prevention Regulations – Authorizations.
PROPOSED REGULATORY TEXT
Notice is given that the National Energy Board, pursuant to subsections 48(2) (see footnote a) and 112(5) (see footnote b) of the National Energy Board Act (see footnote c), proposes to make the annexed National Energy Board Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies.
Interested persons may make representations concerning the proposed Regulations within 30 days after the date of publication of this notice. All such representations must cite the Canada Gazette, Part I, and the date of publication of this notice, and be addressed to Chantal Briand, Regulatory Approaches, National Energy Board, 517 Tenth Avenue SW Calgary, AB, T2R 0A8 (Toll free tel. in Canada: 1-800-899-1265; fax: 403-299-5503; Toll free fax in Canada: 1-877-288-8803; email: damagepreventionregs@neb-one.gc.ca).
Ottawa, March 10, 2016
Jurica Čapkun
Assistant Clerk of the Privy Council
National Energy Board Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies
Interpretation
Definitions
1 The following definitions apply in these Regulations.
authorization means the authorization referred to in subsection 112(1) or paragraph 112(2)(a) of the National Energy Board Act. (autorisation)
facility means any structure, highway, private road, railway, irrigation ditch, drain, drainage system, sewer, dike, telephone line, telegraph line, telecommunication line, line for the transmission of electricity or pipe for the transmission of hydrocarbons or any other substance. (installation)
pipe means a pipe that is part of a pipeline and that is used or is to be used for the transmission of hydrocarbons or any other commodity. (conduite)
prescribed area has the meaning assigned by section 2 of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations. (zone réglementaire)
working day means any day that is not a Saturday or a Sunday or other holiday. (jour ouvrable)
One-Call Centre
Obligation to be a member
2 (1) If a pipeline company operates a pipeline within a geographical area where a one-call centre exists, the pipeline company must be a member of that centre.
One-call centre
(2) A one-call centre is an organization that, for the purposes of protecting the underground infrastructures of its members from damage and ensuring public safety,
- (a) receives locate requests from within a defined geographical area; and
- (b) notifies its members that may be affected by any proposed construction or any proposed activity that would cause a ground disturbance and that are the subject of a locate request of that construction or activity.
Consent
Inform person of decision
3 (1) If a pipeline company receives a request for the written consent referred to in paragraph 7(1)(a) or 10(1)(a) or section 12 of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations, the pipeline company must, within 10 working days after receiving the request, inform the person that made the request whether the consent has been granted or refused and, in the case of a refusal, the reasons for the refusal.
Contents of consent
(2) When a person makes a request to the pipeline company for the written consent referred to in paragraph 7(1)(a) or 10(1)(a) of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations that contains the technical and other information that enable the pipeline company to determine whether the construction or activity would impair the pipeline's safety and security, the pipeline company may grant its consent subject to any conditions necessary for the protection of property and the environment, the safety and security of the public and of the company's employees or the pipeline's safety and security.
Amendment or addition of conditions
(3) At any time during the construction of a facility or the activity that causes a ground disturbance, the pipeline company may add conditions or amend the conditions referred to in subsection (2) if it determines that additions or amendments are necessary to ensure the pipeline's safety and security.
Obligation to Provide Information
Information – application for authorization
4 If a person that intends to construct a facility across, on, along or under a pipeline, engage in an activity that would cause a ground disturbance within the prescribed area of a pipeline or operate a vehicle or mobile equipment across a pipeline has made a request to the pipeline company for the information that is necessary to make an application to the Board for authorization, the pipeline company must, within 10 working days after receiving the request, give the person all the information, and provide all reasonable assistance, that is necessary to prepare the application.
Comments by pipeline company
5 If a pipeline company receives a copy of an application for authorization that has been filed with the Board, the pipeline company must, within 10 working days after receiving the copy of the application, send to the Board its comments on the application.
Obligations Following Request to Locate
Timeline
6 (1) Subject to subsection (2), if a pipeline company receives a request to locate its pipes from a person that intends to construct a facility across, on, along or under a pipeline or engage in an activity that would cause a ground disturbance within the prescribed area, the pipeline company must, within three working days after the day on which the request is made, or any longer period agreed to by the pipeline company and that person,
- (a) inform the person, in writing, of safety practices to be followed while working in the vicinity of its pipes and, in case of a ground disturbance, within the prescribed area;
- (b) mark the location of its pipes in the vicinity of the proposed facility or the prescribed area at maximum intervals of 10 m along each pipe using markings that are clearly visible and distinct from any other markings that may be in the vicinity of the proposed facility or the prescribed area; and
- (c) provide information to the person that clearly explains the significance of the markings.
Markings
(2) The markings must be consistent with the standards for locating a pipeline that are set out in the pipeline company's damage prevention program.
Obligations Respecting Certain Locations
Agricultual activity
7 Even if the condition set out in paragraph 13(1)(a) of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations is met, when the operation of vehicles or mobile equipment across a pipeline at specific locations for the purposes of performing an agricultural activity could impair the pipeline's safety or security, the pipeline company must identify those locations and notify the following persons in writing of those locations:
- (a) landowners of the specific locations in question; and
- (b) persons engaged in agriculture that raise livestock or grow crops, rent or lease the land or work as service providers or employees at the specific locations in question.
Inspections
Inspections and field observations
8 The pipeline company must
- (a) carry out any inspections that are necessary to ensure the pipeline's continued safety and security during an activity that causes a ground disturbance within the prescribed area;
- (b) inspect all exposed pipe prior to any backfilling over a pipe to ensure that no damage to the pipe has occurred; and
- (c) in respect of any inspection carried out under paragraphs (a) and (b), make field observations relating to
- (i) if a pipe was exposed, the clearance between the pipe and the facility and the condition of the pipe at the time of backfilling over the pipe,
- (ii) the compliance with the measures set out in the National Energy Board Pipeline Damage Prevention Regulations – Authorizations,
- (iii) the method used to engage in the activity that caused a ground disturbance, and
- (iv) the occurrence of any unusual events that are related to the construction or activity and that may have had an effect on the pipeline's safety or security.
Detection of deterioration
9 (1) The pipeline company must make any inspections that are necessary to ensure that any deterioration of a facility that might adversely affect a pipe is detected and must notify the facility's owner, in writing, of any deterioration that is detected.
Notification
(2) If an inspection reveals deterioration of a facility that would so impair the safety or security of the pipe as to warrant removal of the facility, the pipeline company must so notify the Board in writing.
Suspension
Grounds
10 (1) The pipeline company may suspend the consent that it granted to construct a facility or to engage in an activity that causes a ground disturbance within the prescribed area if
- (a) the person carrying out the construction of a facility does not comply with the technical details and the conditions referred to in paragraph 7(3)(a) of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations or the instructions referred to in paragraph 7(3)(c) of those Regulations;
- (b) the person engaging in an activity that causes the ground disturbance does not comply with the technical details and the conditions referred to in paragraph 10(3)(a) of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations or the instructions referred to in paragraph 10(3)(d) of those Regulations; or
- (c) work practices might impair the pipeline's safety or security.
Notify Board
(2) If a pipeline company suspends its consent pursuant to subsection (1), it must immediately notify the Board in writing of the suspension and give its reasons for the suspension.
Obligation to Report
Report to Board
11 (1) The pipeline company must immediately report to the Board
- (a) every contravention of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations;
- (b) all damage to its pipe caused or identified during the construction of a facility across, on, along or under a pipeline, the operation, maintenance or removal of a facility, an activity that caused a ground disturbance within the prescribed area or the operation of vehicles or mobile equipment across the pipeline; and
- (c) any activity related to the construction of a facility across, on, along or under a pipeline, an activity that caused a ground disturbance within the prescribed area or the operation of vehicles or mobile equipment across a pipeline that the pipeline company considers could impair the safety or security of the pipe.
Contents of report
(2) The report must include the following information:
- (a) details of any contravention or of any damage, including, in the case of damage, the cause and nature of the damage;
- (b) any concerns that the pipeline company may have regarding the pipeline's safety or security as a result of the construction of the facility, the activity that caused a ground disturbance or the operation of vehicles or mobile equipment across the pipeline; and
- (c) any action the pipeline company intends to take or request.
Records
Facilities and ground disturbances
12 (1) The pipeline company must keep a record of all construction of facilities across, on, along or under a pipeline and of all activities that cause a ground disturbance within the prescribed area for the life of the pipeline, including its abandonment.
Contents of records
(2) The records must include, for each facility or each activity that causes a ground disturbance, as the case may be,
- (a) the name and address of the person that carries out the construction or engages in an activity that causes a ground disturbance;
- (b) the nature and location of the facility or the activity that causes a ground disturbance;
- (c) the dates of commencement and termination of the construction of the facility or the activity that causes a ground disturbance;
- (d) a description of the proposed facility, submitted with the request for the consent;
- (e) a copy of the pipeline company's written consent;
- (f) in respect of the inspections referred to in paragraphs 8(a) and (b), all findings and observations, including
- (i) the name of the person that conducted the inspection,
- (ii) the date and time of the inspection, and
- (iii) any field observations referred to in paragraph 8(c);
- (g) a statement of whether the person that carried out the construction or the person that engaged in an activity that caused a ground disturbance has complied with the measures set out in the National Energy Board Pipeline Damage Prevention Regulations – Authorizations; and
- (h) the details of any abandonment, removal or alteration of the facility.
Consent — crossings
(3) The pipeline company must keep a record that contains a copy of the written consents granted by the pipeline company for the purposes of section 12 of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations for the life of the pipeline or, if there is an expiry date set out in the consent, for a period of 12 months from the day on which the consent expires.
Locations
(4) The pipeline company must keep a record of the locations that are identified under section 7.
Duty to make records available
13 Every pipeline company that is required by these Regulations to keep records must make the records, and all other materials necessary to verify the information in those records, available to officers of the Board and other persons authorized by the Board for that purpose and must give the Board and other authorized persons any assistance necessary to inspect the records.
List
14 On the request of the Board, the pipeline company must provide the Board with
- (a) a list of every written consent granted for the purposes of section 12 of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations;
- (b) a list of every written consent granted by the pipeline company with respect to the construction of a facility or an activity that causes a ground disturbance and the information referred to in paragraphs 12(2)(a) to (c) with respect to the consent; and
- (c) a list of every permission granted by the pipeline company for the purposes of the National Energy Board Pipeline Crossing Regulations, Part I and the information referred to in paragraphs 11(2)(a) to (c) of the National Energy Board Pipeline Crossing Regulations, Part II with respect to the permission.
Guidelines
Request for consent
15 Every pipeline company must develop and maintain detailed guidelines setting out the technical and other information to be included in the requests for the written consent referred to in paragraph 7(1)(a) or 10(1)(a) of the National Energy Board Pipeline Damage Prevention Regulations – Authorizations and must make those guidelines public.
Damage Prevention Program
Minimum content
16 The damage prevention program that a pipeline company is required to develop, implement and maintain under section 47.2 of the National Energy Board Onshore Pipeline Regulations must include
- (a) an ongoing public awareness program to inform the public
- (i) of the presence of a pipeline,
- (ii) on how to work safely near a pipeline,
- (iii) on how to report an unexpected situation related to a pipeline that could endanger life or cause substantial property or environmental damage that requires immediate action,
- (iv) on how to report any contact with a pipe or its coating, whether or not the pipe was damaged,
- (v) on how to report any damage to a pipe,
- (vi) of the services of a one-call centre if one exists within the relevant geographical area,
- (vii) on the necessity for authorization when constructing a facility across, on, along or under a pipeline, engaging in an activity that causes a ground disturbance within the prescribed area or operating vehicles or mobile equipment across a pipeline,
- (viii) of the information to be provided in a request for the consent to construct a facility across, on, along or under a pipeline, to engage in an activity that causes a ground disturbance within the prescribed area or to operate a vehicle or mobile equipment across a pipeline, and
- (ix) on the requirement to make a locate request and how to make a locate request in the relevant geographical area;
- (b) ongoing monitoring of any changes in the use of the land on which a pipeline is located and the land that is adjacent to that land;
- (c) ongoing monitoring of any change in the landowner of the land on which a pipeline is located;
- (d) a process to ensure a timely response to locate requests;
- (e) standards for locating a pipeline; and
- (f) a process for managing requests for the consent to construct a facility across, on, along or under a pipeline, to engage in an activity that causes a ground disturbance within the prescribed area or to operate a vehicle or mobile equipment across the pipeline.
Transitional Provisions
Section 11 – former Regulations
17 Section 11 of the National Energy Board Pipeline Crossing Regulations, Part II, as it read immediately before the day on which these Regulations come into force, continues to apply to any person to which that section applied.
Section 14 – former Regulations
18 Section 14 of the National Energy Board Pipeline Crossing Regulations, Part II, as it read immediately before the day on which these Regulations come into force, continues to apply with respect to the permissions referred to in sections 15 and 16 of National Energy Board Pipeline Damage Prevention Regulations – Authorizations.
Application Prior to Publication
Statutory Instruments Act
19 For the purposes of paragraph 11(2)(a) of the Statutory Instruments Act, these Regulations apply before they are published in the Canada Gazette.
Repeal
20 The National Energy Board Pipeline Crossing Regulations, Part II (see footnote 1) are repealed.
Coming into Force
S.C. 2015, c. 21
21 These Regulations come into force on the first day on which both sections 15 and 34 of the Pipeline Safety Act are in force, but if they are registered after that day, they come into force on the day on which they are registered.
[12-1-o]