Canada Gazette, Part I, Volume 152, Number 45: DEPARTMENT OF THE ENVIRONMENT
November 10, 2018
DEPARTMENT OF THE ENVIRONMENT
CANADIAN ENVIRONMENTAL PROTECTION ACT, 1999
Notice requiring the preparation and implementation of pollution prevention plans in respect of hydrazine related to the electricity sector
Pursuant to section 56 of the Canadian Environmental Protection Act, 1999 (hereinafter referred to as the "Act"), the Minister of the Environment published in the Canada Gazette, Part I, on April 18, 2015, the Proposed notice requiring the preparation and implementation of pollution prevention plans in respect of hydrazine related to the electricity sector.
Whereas persons were given the opportunity to file comments with respect to the proposed Notice for a comment period of 60 days; and
Whereas the Minister of the Environment has considered all comments received,
Notice is hereby given that, under subsection 56(1) of the Act, the Minister of the Environment requires any person or class of persons described in section 2 of the Notice to prepare and implement a pollution prevention plan in respect of hydrazine, which is specified in Schedule 1 of the Act.
The Minister of the Environment will measure the performance of the Notice, throughout the preparation and implementation periods, in order to determine its effectiveness in meeting the risk management objectives set out in section 4 of the Notice. This evaluation will determine whether additional measures, including regulations, may be required.
More information on pollution prevention planning can be found in the Pollution Prevention Planning Provisions of Part 4 of the Canadian Environmental Protection Act, 1999: Guidelines for Implementation. These guidelines and other information relating to pollution prevention and pollution prevention planning can also be found in the "Pollution Prevention Planning Notices" section of the Government of Canada website.
Catherine McKenna
Minister of the Environment
NOTICE REQUIRING THE PREPARATION AND IMPLEMENTATION OF POLLUTION PREVENTION PLANS IN RESPECT OF HYDRAZINE RELATED TO THE ELECTRICITY SECTOR
Notice is hereby given that, pursuant to the provisions of subsection 56(1) of Part 4 of the Act, the Minister of the Environment requires any person or class of persons described in section 2 of this Notice, to prepare and implement a pollution prevention plan in respect of hydrazine, which is specified on the List of Toxic Substances in Schedule 1 of the Act.
1. Definitions
The definitions in this section apply to this Notice.
- "Act" means the Canadian Environmental Protection Act, 1999 (CEPA).
- "Effluent" means a process stream released at any final discharge point of the facility.
- "Electricity sector" means a group of companies engaged in the generation and transmission of electricity, and whose primary purpose is the generation of electricity for distribution or commercial sale.
- "Facility" includes any industrial site that generates electricity primarily for distribution or commercial sale, and excludes facilities where electricity is generated with a non-thermal process.
- "Final discharge point" means an identifiable release point, prior to any dilution by receiving water, beyond which the facility operator no longer exercises control over quality of the effluent.
- "Hydrazine" means the substance with the Chemical Abstracts Service Registry Number (CAS RN footnote 1) 302-01-2, and the Domestic Substances List name "Hydrazine".
- "Large freshwater body" means a freshwater body, other than the Great Lakes, where the ratio of receiving water flow to effluent flow is greater than 100:1, calculated using the 10th percentile of the receiving water flow (or equivalent), and the highest expected effluent flow containing hydrazine.
- "Minister" means the Minister of the Environment.
- "Notice" means the Notice requiring the preparation and implementation of pollution prevention plans in respect of hydrazine related to the electricity sector.
- "Normal operating conditions" means any activity that results in release of effluent containing hydrazine, other than during start-up, during shutdown, and during emergency circumstances or accidental releases. This includes, but is not limited to, steam generation systems, feed water systems, and condensate systems where oxygen scavengers are used for water chemistry optimization.
- "Operator" means the person who operates or has charge, management or control of a facility.
- "Plan" means a pollution prevention plan.
- "Pollution prevention," as defined in section 3 of the Act, means the use of processes, practices, materials, products, substances or energy that avoid or minimize the creation of pollutants and waste and reduce the overall risk to the environment or human health.
- "Receiving water" means any body, stream or channel of water, but excluding water used in the equipment of the facility, or for on-site storage or treatment of effluents.
- "Techniques" includes both the facility equipment used in the process and how the process is operated. It includes, but is not limited to, matters such as the number of employees, their qualifications and experience, working methods, training, supervision and the manner in which the process is performed. It also includes the design, construction, layout and maintenance of the facility.
2. Person or class of persons required to prepare and implement a plan
- (1) This Notice applies to any person or class of persons who, on the date of publication of the Notice and anytime thereafter, operates a facility in the electricity sector that, under normal operating conditions and at any final discharge point, has a concentration of hydrazine that is higher than the following target levels:
- 26 ug/L, if discharged to a Great Lake;
- 26 ug/L, if discharged to a large freshwater body;
- 2.6 ug/L, if discharged to a freshwater body that is not a large freshwater body or a Great lake; or
- 2.0 ug/L, if discharged to sea water.
- (2) The Notice applies to any person or class of persons who is the successor or assign of the persons identified in subsection 2(1).
3. Activities in relation to which the plan is to be prepared
The Minister requires any person or class of persons identified in section 2 of the Notice to prepare and implement a plan in relation to the use and release of hydrazine.
4. Factors to consider in preparing the plan
The Minister requires any person or class of persons identified in section 2 of the Notice to consider the following factors when preparing their plan:
- (1) Hydrazine was classified as a toxic substance under paragraphs 64(a) and 64(c) of the Act and has been added to the List of Toxic Substances in Schedule 1 of the Act on September 20, 2012. The final Screening Assessment Report concluded that hydrazine is entering or may enter the environment in a quantity or concentration or under conditions that have or may have an immediate or long-term harmful effect on the environment or its biological diversity or that constitute or may constitute a danger in Canada to human life or health. The final Screening Assessment Report for hydrazine is available on the Government of Canada website.
- (2) The risk management objective for hydrazine is to achieve and maintain a total hydrazine concentration in effluent at each final discharge point of the facility that is less than or equal to the target levels specified as per subsection 2(1).
- (3) Priority must be given to pollution prevention activities, by utilizing techniques or best available technologies as a means to address the release of hydrazine to the aquatic environment.
- (4) All effluent streams from industrial processes and cooling systems, all surface drainage streams, and all groundwater-sourced effluent streams that can contain hydrazine under normal operating conditions should be addressed by the Plan. The Plan should include a map identifying and labelling each final discharge point, as well as a description of each final discharge point.
- (5) Conduct sampling of effluent for analysis for each final discharge point of the facility that contains or may contain hydrazine and prior to any dilution by receiving water.
- (a) Sampling should at all times be representative of the highest expected concentration of hydrazine resulting from normal operating conditions. Although the sampling frequency may be aligned with existing reporting requirements under other jurisdictions, samples should be collected and analyzed a minimum of four times per year for each final discharge point that contains or may contain hydrazine. Sampling and handling of the samples should be conducted following best practices for the applicable analytical method in order to minimize the degradation of hydrazine;
- (b) Any analysis of hydrazine performed for the purposes of this Notice must be performed by a laboratory that meets the following conditions at the time of analysis:
- (i) The laboratory
- (A) is accredited under the International Organization for Standardization standard ISO/IEC 17025, entitled General requirements for the competences of testing and calibration laboratories, by an accrediting body that is a signatory to the International Laboratory Accreditation Cooperation Mutual Recognition Arrangement,
- (B) is accredited under the Environmental Quality Act, CQLR, c. Q-2, and the scope of its accreditation includes the analysis of hydrazine, or
- (C) is an equivalent laboratory to an accredited laboratory described in clause (A) and (B),
- (ii) The laboratory analysis should be performed according to an analytical method that achieves a limit of quantification at or below the target levels specified in subsection 2(1).
- (i) The laboratory
5. Period within which the plan is to be prepared
- (1) For a person or class of persons subject to the Notice on the date of publication in the Canada Gazette, Part I, the Minister requires that the plan be prepared and implementation initiated no later than 12 months from the publication date of the Notice.
- (2) For a person or class of persons becoming subject to the Notice after the date of publication in the Canada Gazette, Part I, the Minister requires that the plan be prepared and implementation initiated no later than 12 months from becoming subject to the Notice.
6. Period within which the plan is to be implemented
- (1) For a person or class of persons subject to the Notice on the date of publication in the Canada Gazette, Part I, the Minister requires that the plan be implemented no later than 36 months from the date of publication of the Notice.
- (2) For a person or class of persons becoming subject to the Notice after the date of publication in the Canada Gazette, Part I, the Minister requires that the plan be implemented no later than 36 months of the person or class of persons becoming subject to the Notice.
7. Content of the plan
A person or class of persons identified in section 2 of the Notice is to determine the appropriate content of that person's plan; however, the plan must meet all the requirements of the Notice. The plan must also contain the information required to file the Declaration of Preparation referred to in section 9 of the Notice and be able to generate the information required to file the Declaration of Implementation referred to in section 10.
8. Requirement to keep the plan and record keeping
Under section 59 of the Act, any person or class of persons identified in section 2 of the Notice must keep a copy of the plan at the location in Canada in relation to which the plan is prepared. Where a single plan is prepared for more than one facility, a copy of that plan must be kept at each location.
Any person or class of persons identified in section 2 of the Notice must keep the plan and any records pertaining to the plan for a minimum of five years following the period referred to in section 6 of the Notice.
9. Declaration of Preparation
Under subsection 58(1) of the Act, any person or class of persons identified in section 2 of the Notice must file, within 30 days after the end of the period within which the plan is to be prepared as specified in section 5 or within 30 days after the period extended under section 13, a written "Declaration that a Pollution Prevention Plan Has Been Prepared and Is Being Implemented — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 58(1) of CEPA)". This Declaration must be submitted to the Minister, using the form that the Minister provides that contains the information set out in Schedule 1 of the Notice. Where a person or class of persons has prepared a single plan for several facilities, a separate Declaration of Preparation must be submitted for each facility.
10. Declaration of Implementation
Under subsection 58(2) of the Act, any person or class of persons identified in section 2 of the Notice must file within 30 days after the end of the period within which the plan is to be implemented as specified in section 6 or within 30 days after the end of the period extended under section 13, a written "Declaration that a Pollution Prevention Plan Has Been Implemented — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 58(2) of CEPA)". This Declaration must be submitted to the Minister, using the form that the Minister provides that contains the information set out in Schedule 5 of the Notice. Where a person or class of persons has prepared a single plan for several facilities, a separate Declaration of Implementation must be submitted for each facility.
11. Filing of amended Declarations
Under subsection 58(3) of the Act, where a person or class of persons specified in section 2 of the Notice has filed a Declaration of Preparation or a Declaration of Implementation, referred to in sections 9 and 10 of the Notice, and the Declaration contains information that, at any time after the filing, has become false or misleading, that person or class of persons must file an amended Declaration to the Minister within 30 days after the time that the information became false or misleading, using the appropriate form referred to in section 9 or 10 of the Notice.
12. Use of a plan prepared or implemented for another purpose
Under subsection 57(1) of the Act, a person or class of persons may use a pollution prevention plan prepared or implemented for another purpose to satisfy the requirements of the Notice. Under subsection 57(2) of the Act, where a person or class of persons uses a plan that does not meet all the requirements of the Notice, the person or class of persons must either amend the plan so that it meets all of those requirements or prepare an additional plan that meets the remainder of those requirements. A person or class of persons using existing plans must still file the Declaration of Preparation referred to in section 9 of the Notice, the Declaration of Implementation referred to in section 10 of the Notice, and, where applicable, any amended declarations referred to in section 11 of the Notice.
13. Extension of time
Under subsection 56(3) of the Act, where the Minister is of the opinion that further time beyond the period referred to in section 5 is needed to prepare the plan, or that further time beyond the period referred to in section 6 is needed to implement the plan, the Minister may extend the period for a person or class of persons who submits a written "Request for Time Extension — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 56(3) of CEPA)". The written request must be submitted using the form that the Minister provides that contains the information set out in Schedule 3 of the Notice, and be made before the expiry of the time period referred to in section 5 or section 6 or before the expiry of any extended period.
14. Application for waiver of factors to consider
Under subsection 56(5) of the Act, the Minister may waive the requirement for a person or class of persons to consider a factor in preparing the plan specified in section 4 where the Minister is of the opinion that it is neither reasonable nor practicable to consider a factor on the basis of reasons provided by that person or class of persons when submitting a written "Request for Waiver of the Requirement to Consider a Factor or Factors — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 56(5) of CEPA)". This written request must be submitted using the form that the Minister provides and must contain the information set out in Schedule 2 of the Notice. Such a request must be made before the expiry of the period within which the plan is to be prepared as referred to in section 5 of the Notice or before the expiry of any extended period.
15. Performance measurement and evaluation of the Notice
Performance measurement of the Notice will be conducted after every reporting cycle in order to evaluate the effectiveness of the Notice in meeting its intended objectives. Performance reports summarizing the overall results to date will be posted online on the Pollution Prevention Planning section of the Government of Canada website.
The Minister will evaluate the effectiveness of the Notice with respect to the risk management objective set out in section 4 of the Notice.
The Minister will determine whether other measures, including regulations, are needed to further prevent or reduce negative impacts of hydrazine on the environment and human health.
16. Resources
Guidance on preparing pollution prevention plans may be obtained from
- the Pollution prevention planning notices section of the Government of Canada website.
Additional information and guidance on pollution prevention can be found on
- the Pollution prevention section of the Government of Canada website; and
- the Pollution prevention resource finder website.
17. Notice Reference Code: P2Hydrazine
For administrative purposes, all communication with Environment Canada concerning the Notice should refer to the following Notice Reference Code: P2Hydrazine.
18. Public Disclosure of Information and forms
The Minister of the Environment intends to publish information submitted in response to the Notice in schedules 1 and 5 in the Pollution Prevention Planning section of the Government of Canada website.
Under section 313 of the Act, a person or class of persons submitting information to the Minister may submit with the information a written request that specific information be treated as confidential. A person or class of persons submitting such a request should also include the reasons for every section where confidentiality is being requested.
The Notice includes the following forms:
- Schedule 1: Declaration that a Pollution Prevention Plan Has Been Prepared and Is Being Implemented — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 58(1) of CEPA);
- Schedule 2: Request for Waiver of the Requirement to Consider a Factor or Factors — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 56(5) of CEPA);
- Schedule 3: Request for Time Extension — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 56(3) of CEPA);
- Schedule 4: Interim Progress Reports are not required for this Notice; and
- Schedule 5: Declaration that a Pollution Prevention Plan Has Been Implemented — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 58(2) of CEPA).
Forms referred to in the Notice (schedules 1 to 5) are published as part of the Notice and should be filled out electronically using the Pollution Prevention Planning Online Reporting Tool through the Single Window Information Manager system.
For guidance on how to complete the schedules, please refer to the Instructions for Completing the Schedules Required by the Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector.
For additional guidance on how to complete the schedules online, please refer to the How to use the P2 notice reporting tool.
19. Environment Canada contact information
For technical questions about the Notice, please contact
Electricity and Combustion Division
Environment Canada
351 Saint-Joseph Boulevard
Gatineau, Quebec
K1A 0H3
Email: ec.electricite-electricity.ec@canada.ca
For more information about pollution prevention planning, please contact
Regulatory Innovation and Management Systems
c/o Innovative Measures Section
Environment Canada
351 Saint-Joseph Boulevard, 20th Floor
Gatineau, Quebec
K1A 0H3
Telephone (toll-free): 1-844-580-3637
Fax: 819-420-7386 or toll-free: 1-844-580-3638
Email: ec.planp2-p2plan.ec@canada.ca
EXPLANATORY NOTE
(This note is not part of the Notice.)
Compliance with the Canadian Environmental Protection Act, 1999 (hereinafter referred to as the "Act") is mandatory pursuant to subsections 272(1) and 272.1(1) of the Act. Subsections 272(2), (3) and (4) and 272.1(2), (3) and (4) of the Act set the penalties for persons who commit an offence under the Act. Offences include the offence of failing to comply with an obligation arising from the Act and the offence of providing false or misleading information. Penalties for offences can result, upon conviction (either summary conviction or indictment), in fines of not more than $12 million, imprisonment for a term of not more than three years, or both.
The current text of the Act, including the most recent amendments, is available on the Department of Justice Canada website.
The Act is enforced in accordance with the Compliance and Enforcement Policy for the Canadian Environmental Protection Act, 1999.
Suspected violations under the Act can be reported to the Enforcement Branch by email at environmental.enforcement@canada.ca.
NOTE: Please contact Environment Canada for more information about electronic reporting, as provided in sections 16 to 19 in the Notice. Do not fill out this form as it appears in the Canada Gazette; it is for information only. The format and design of the online version may slightly differ from this version.
Schedule 1: Declaration that a Pollution Prevention Plan Has Been Prepared and Is Being Implemented — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 58(1) of CEPA)
Notice Reference Code: P2Hydrazine
For guidance on how to complete this Declaration, please refer to the Instructions for Completing the Schedules.
Is this an amendment to a Declaration previously submitted? ☐ Yes ☐ No
If yes, please specify the amended part(s) and reason(s) below. In addition, please complete Parts 1.0 and 9.0 and any other parts of this Declaration for which previously reported information has become false or misleading. Previously reported information that is unchanged need not be resubmitted.
If no, please proceed to Part 1.0 of this Declaration.
Amendment Part(s)
Please specify the part(s) of the Declaration that you would like to amend.
Amendment Reason(s)
Please specify the reason(s) for each of the amendments that you would like to make.
1.0 Information on the Person or Class of Persons Subject to the Notice
Company
Company name: _______________________________________________________________________
Canadian Federal Business Number: _________________________________________________________
Facility Information
Facility Name: ________________________________________________________________________
Physical Address
Unit Number: ________ Street Number: ________ Street Name: ____________________________________
Street Type: ___________________ Street Direction: ______________ City: _________________________
Province/Territory: ___________________ Postal Code: ____________ Country: _______________________
Mailing Address
Same as Physical Address ☐
PO Box: _______________ Rural Route Number: _________ Unit/Suite/Building Number: _________________
Street Number: ____________ Street Name: _______________________________ Street Type: ___________
Street Direction: _______ City: ____________________________________________________________
Province/Territory: ____________________ Postal Code: ________________ Country: __________________
National Pollutant Release Inventory (NPRI) ID: __________________________________________________
North American Industry Classification System (NAICS) code: ________________________________________
Technical Contact
Name: ___________________________________________
Position/Job Title: ___________________________________
Mailing Address
PO Box: _______________ Rural Route Number: _________ Unit/Suite/Building Number: _________________
Street Number: ____________ Street Name: _______________________________ Street Type: ___________
Street Direction: _______ City: ____________________________________________________________
Province/Territory: ____________________ Postal Code: ________________ Country: __________________
Telephone Number: ____________________ Extension: ________ Fax Number: _______________________
Email: ______________________________________________________________________________
General Contact
Same as Facility Technical Contact ☐
Name: ___________________________________________
Position/Job Title: ___________________________________
Mailing Address
PO Box: _______________ Rural Route Number: _________ Unit/Suite/Building Number: _________________
Street Number: ____________ Street Name: _______________________________ Street Type: ___________
Street Direction: _______ City: ____________________________________________________________
Province/Territory: ____________________ Postal Code: ________________ Country: __________________
Telephone Number: ____________________ Extension: ________ Fax Number: _______________________
Email: ______________________________________________________________________________
2.0 Use of Existing Plans
Prior to this Notice, did your facility have a Pollution Prevention Plan (P2 Plan) in regards to hydrazine? ☐ Yes ☐ No
If yes, the P2 Plan was previously prepared:
- on a voluntary basis? ☐ Yes ☐ No
- for another government or under another Act of Parliament? ☐ Yes ☐ No
- If yes, please identify the other government requirement(s) or Act of Parliament.
- for other reasons? ☐ Yes ☐ No
- If yes, please specify the other reasons.
If a P2 Plan was previously prepared, did you use that P2 Plan (all or in part) to meet the requirements of the Notice? ☐ Yes ☐ No
3.0 Information on the Size of the Receiving Freshwater Body (other than the Great Lakes)
Did this facility release an effluent containing hydrazine during the Preparation Year to a large freshwater body, as defined in section 1 of the Notice?
☐ Yes ☐ No
If yes, the table below must be completed separately for each effluent that was released to a large freshwater body.
Name of discharge point: _________________________________________________________________
Name of receiving water body: ______________________________________________________________
Please specify the ratio of receiving water flow to effluent flow calculated using the 10th percentile of the receiving water flow (or equivalent), and the highest expected effluent flow containing hydrazine.
Flow Rate | Flow Rate Unit | |
---|---|---|
Receiving water | ||
Effluent | ||
Ratio | n/a |
Estimation Methods
- (a) Effluent Estimation Method:
- ☐ M4 Continuous Flow Rate Monitoring Systems
- ☐ M5 Process Flowsheet Analysis
- ☐ M6 Process Flow Diagram
- ☐ C Mass Balance Analysis
- ☐ O Engineering Estimates
- ☐ X Other
- (b) Receiving Water Estimation Method:
- ☐ E3 Government of Canada Hydrometric Data
- ☐ Other
4.0 Baseline Information
Indicate the Preparation Year for which you are reporting: from (Year-Month-Day) to (Year-Month-Day).
All information provided in this Declaration will refer to this Preparation Year.
In Part 4.0, where indicated, use the following Basis of Estimate Codes to describe how each quantity reported in this part of the Declaration was determined:
- M1 Continuous Emission Monitoring Systems
- M2 Predictive Emission Monitoring
- M3 Source Testing
- C Mass Balance
- E1 Site-specific Emission Factor
- E2 Published Emission Factor
- O Engineering Estimates
- X Other
4.1 On-site Uses
Did this facility use Hydrazine on site in the Preparation Year? ☐ Yes ☐ No
If yes, please specify the Use/Process (select all that apply).
☐ As a physical or chemical processing aid (e.g. boiler water chemistry control)
☐ Other
Total Quantity of all On-site Uses for the Preparation Year (kg) |
Basis of Estimate Code |
---|---|
4.2 Releases to Receiving Water
Did this facility release hydrazine to receiving water during the Preparation Year?
☐ Yes ☐ No
If yes, report the quantity of all releases of hydrazine to receiving water.
Type of Releases to Waters | Quantity Released During the Preparation Year (kg) |
Basis of Estimate Code |
---|---|---|
(a) Release to receiving water from all final discharge points | ||
(b) Release to receiving water not through designated final discharge points (spills, leaks) | ||
TOTAL | n/a |
4.3 Release to On-site Water Treatment System
Did this facility release hydrazine to an on-site water treatment system during the Preparation Year?
☐ Yes ☐ No
If yes, report the quantity.
Release to On-site Water Treatment System (Kg) |
Basis of Estimate Code |
---|---|
4.4 Off-site Transfers for Disposal
Did this facility transfer hydrazine off-site for disposal in the Preparation Year?
☐ Yes ☐ No
If yes, report the quantity of all off-site transfers for disposal.
Type of Transfers for Disposal | Quantity Transferred for the Preparation Year (kg) |
Basis of Estimate Code | Facility Name and Address |
---|---|---|---|
(a) Physical treatment | |||
(b) Chemical treatment | |||
(c) Biological treatment | |||
(d) Incineration/thermal | |||
(e) Containment | |||
(f) Municipal Sewage Treatment Plant (MSTP) | |||
(g) Underground injection | |||
(h) Land treatment | |||
(i) Other | |||
TOTAL | n/a | n/a |
4.5 Sampling and Analysis — Concentration of Hydrazine at Final Discharge Points
The table below must be completed separately for each Final Discharge Point.
Name of discharge point: _________________________________________________________________
Name of receiving water body: ______________________________________________________________
Sample | Concentration of Hydrazine at the Final Discharge Point (µg/L) | Date of Sampling | Date of Laboratory Analysis | Laboratory Name, City and Telephone Number | Laboratory Accreditation Number |
---|---|---|---|---|---|
No. 1 | |||||
No. 2 | |||||
No. 3 | |||||
No. 4 | |||||
Average | n/a |
Comments
5.0 Anticipated Actions and Anticipated Results
5.1 Anticipated Actions
Parts 5.1.1 through 5.1.5 must be completed separately for each anticipated action. (i.e. Part 5.1 will be completed as many times as there are actions taken to date to report).
5.1.1 Action to be taken
What is the name of the action to be taken in implementing the Pollution Prevention Plan? ____________________
___________________________________________________________________________________
What is the current status of this action?
☐ Planned/To Be Initiated
☐ In Progress
☐ Completed
Describe the anticipated action to be taken.
For the anticipated action reported above, identify whether it represents pollution prevention method(s) listed in Part 5.1.2 OR environmental protection method(s) listed in Part 5.1.3.
5.1.2 Types of Pollution Prevention Methods (select all that apply)
☐ Material or feedstock substitution
☐ Product design or reformulation
☐ Equipment or process modifications
☐ Spill and leak prevention
☐ On-site reuse, recycling or recovery
☐ Inventory management or purchasing techniques
☐ Good operating practices or training
☐ Other (please specify): ____________________________________
5.1.3 Types of Environmental Protection Methods (select all that apply)
☐ Energy recovery
☐ Off-site recycling
☐ Incineration with energy recovery
☐ Waste treatment
☐ Pollution control
☐ Disposal
☐ Other (please specify): ________________________
5.1.4 Anticipated Changes: ________________________________
5.1.5 Baseline Elements Affected by Anticipated Changes
☐ Quantity of on-site uses
☐ Releases to receiving water from all final discharge points
☐ Releases to receiving water not through designated final discharge point
☐ Releases to on-site water treatment system
☐ Quantity of off-site transfers for disposal
☐ Concentration in effluent at final discharge points
5.1.6 Planned Completion Date for Anticipated Action (YYYY-MM-DD): _____________________________________
5.2 Total Anticipated Results
Report the total anticipated change from ALL anticipated actions described in Part 5.1 of this Declaration.
Type of Use/Release/Transfer | Total Anticipated Change Relative to the Preparation Year (kg) |
Total Anticipated Change Relative to the Preparation Year (%) |
---|---|---|
On-site uses | ||
Releases to receiving water from all final discharge points | ||
Releases to receiving water not through designated final discharge points | ||
Releases to on-site water treatment system | ||
Off-site transfers for disposal | ||
Total |
5.3 Detailed Anticipated Results Information
Report the total anticipated change from ALL anticipated actions described in Part 5.1 of this Declaration.
Final Discharge Point | Total Anticipated Change of the Concentration Relative to the Preparation Year (μg/L) | Total Anticipated Change of the Concentration Relative to the Preparation Year (%) |
---|---|---|
1 | ||
2 | ||
3 | ||
4 | ||
5 | ||
6 | ||
7 | ||
Total | n/a | n/a |
6.0 Monitoring
Describe the anticipated monitoring that will be used to track progress in implementing the Pollution Prevention Plan.
7.0 Risk Management Objective
Do you anticipate meeting the Risk Management Objective?
☐ Yes ☐ No
Describe how the elements of the Pollution Prevention Plan will meet the risk management objective for hydrazine. If no, explain why.
8.0 Factors to Consider
Describe how the factors to consider set out in subsections 4(3) to 4(5) of the Notice were taken into account when preparing the Pollution Prevention Plan.
4(3) Priority to Pollution Prevention Activities
4(4) Coverage of Effluent Streams and their Identification
4(5)(a) Sampling Activities
4(5)(b) Analysis Activities
9.0 Certification
The information submitted in this Schedule will be made available to the public except for the
- general and technical contact information;
- parts that you requested confidentiality by clicking on the padlock icon on previous screens; and
- all information appearing on this page.
☐ I hereby certify that a Pollution Prevention Plan in respect of hydrazine has been prepared and is being implemented and that the information provided in this Declaration is true, accurate and complete.
Name: _________________________________________________
Title/Position: ____________________________________________
Email: _________________________________________________
Date: __________________________________________________
General Comments
NOTE: Please contact Environment Canada for more information about electronic reporting, as provided in sections 16 to 19 in the Notice. Do not fill out this form as it appears in the Canada Gazette; it is for information only. The format and design of the online version may slightly differ from this version.
Schedule 2: Request for Waiver of the Requirement to Consider a Factor or Factors — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 56(5) of CEPA)
Notice Reference Code: P2Hydrazine
Contacts (Part 1.0)
Company
Company Name: ______________________________________________________________________
Canadian Federal Business Number: ________________________________________________________
Facility Information
Facility Name: _______________________________________________________________________
Physical Address
Unit: __________________ Street Number: __________________ Street Name: _______________________
Street Type: _______________ Street Direction: ________________________________________________
City: ____________________ Province/Territory: ___________________________ Postal Code: __________
Country: ____________________________________________________________________________
Mailing Address Same as Physical Address ☐
PO Box: _________ Rural Route Number: _______________ Unit: _________________ Street Number: _________________
Street Name: _________________ Street Type: ______________ Street Direction: _______________________
City: ___________________ Province/Territory: _____________________ Postal Code: _________________
Country: ____________________________________________________________________________
National Pollutant Release Inventory (NPRI) ID: _________________________________________________
Six-digit North American Industry Classification System (NAICS) code: __________________________________
Facility Technical Contact
Name: ________________________________ Position/Job Title: _________________________________
Mailing Address: _____________________ Telephone Number: ______________ Fax Number: _____________
Email: ______________________________________________________________________________
General Contact Same as Facility Technical Contact ☐
Name: ______________________________ Position/Job Title: ___________________________________
Mailing Address: ______________________ Telephone Number: ________________ Fax Number: ___________
Email: ______________________________________________________________________________
Factor(s) for Which a Waiver is Being Requested (Part 2.0)
Identify for which factor(s) listed in the Notice a waiver is being requested.
Rationale for Request (Part 3.0)
Explain why it would not be reasonable or practicable to consider each factor for which a waiver is being requested.
Explain how the outcome of the Pollution Prevention Plan will be affected if this or these "factor(s) to consider" is (are) not taken into account.
Identify which, if any, additional factor(s) you propose to consider in preparing the Pollution Prevention Plan (optional).
Certification (Part 4.0)
☐ I hereby certify that the information provided in this Request is true, accurate and complete.
Name (required): _________________________________________
Title/Position (required): ___________________________________
Email (required): _________________________________________
General Comments
NOTE: Please contact Environment Canada for more information about electronic reporting, as provided in sections 16 to 19 in the Notice. Do not fill out this form as it appears in the Canada Gazette; it is for information only. The format and design of the online version may slightly differ from this version.
Schedule 3: Request for Time Extension — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 56(3) of CEPA)
P2 Notice Reference Code: P2Hydrazine
Contacts (Part 1.0)
Company
Company Name: ______________________________________________________________________
Canadian Federal Business Number: _________________________________________________________
Facility Information
Facility Name: ________________________________________________________________________
Physical Address
Unit: _____________________ Street Number: _________________ Street Name: _____________________
Street Type: ___________________ Street Direction: ____________________________________________
City: ____________________ Province/Territory: ___________________ Postal Code: __________________
Country: ____________________________________________________________________________
Mailing Address Same as Physical Address ☐
Unit: _________ PO Box: __________ Rural Route Number: _______________ Street Number: _____________
Street Name: _____________ Street Type: _____________ Street Direction: ____________________________
City: __________________ Province/Territory: ___________________ Postal Code: ____________________
Country: ____________________________________________________________________________
National Pollutant Release Inventory (NPRI) ID: _________________________________________________
Six-digit North American Industry Classification System (NAISC) code: __________________________________
Facility Technical Contact
Name: ______________________________ Position/Job Title: ___________________________________
Mailing Address: _______________________ Telephone Number: ______________ Fax Number: ____________
Email: ______________________________________________________________________________
General Contact Same as Facility Technical Contact ☐
Name: _________________________________ Position/Job Title: ________________________________
Mailing Address: __________________ Telephone Number: _______________ Fax Number: _______________
Email: ______________________________________________________________________________
Request for Time Extension (Part 2.0)
Identify for which of the following a time extension is being requested (choose one):
☐ to prepare a Pollution Prevention Plan
☐ to implement a Pollution Prevention Plan
Are you requesting to extend a time extension already granted by Environment and Climate Change Canada?
☐ Yes ☐ No
We request that the date be extended to: _____________________ (specify exact date – YYYY-MM-DD)
Rationale for Request (Part 3.0)
Explain why additional time is needed to prepare or implement a Pollution Prevention Plan.
Certification (Part 4.0)
☐ I hereby certify that the information provided in this Request is true, accurate and complete.
Name (required): _________________________________________
Title/Position (required): ___________________________________
Email (required): _________________________________________
General Comments
NOTE: Please contact Environment Canada for more information about electronic reporting, as provided in sections 16 to 19 of the Notice. Do not fill out this form as it appears in the Canada Gazette; it is for information only. The format and design of the online version may slightly differ from this version.
Schedule 5: Declaration that a Pollution Prevention Plan Has Been Implemented — Pollution Prevention Planning Notice in Respect of Hydrazine Related to the Electricity Sector (subsection 58(2) of CEPA)
Notice Reference Code: P2Hydrazine
For guidance on how to complete this Declaration, please refer to the Instructions for Completing the Schedules.
Is this an amendment to a Declaration previously submitted? ☐ Yes ☐ No
If yes, please specify the amended parts and reasons below. In addition, please complete Parts 1.0 and 9.0 and any other parts of this Declaration for which previously reported information has become false or misleading. Previously reported information that is unchanged need not be resubmitted.
If no, please proceed to Part 1.0 of this Declaration.
Amendment Part(s)
Please specify the parts of the Declaration that you would like to amend.
Amendment Reason(s)
Please specify the reason for each of the amendments that you would like to make.
1.0 Information on the Person or Class of Persons Subject to the Notice
Company
Company name: _______________________________________________________________________
Canadian Federal Business Number: _________________________________________________________
Facility Information
Facility Name: ________________________________________________________________________
Physical Address
Unit Number: ________ Street Number: ________ Street Name: _____________________________________
Street Type: ___________________ Street Direction: ______________ City: __________________________
Province/Territory: ___________________ Postal Code: ____________ Country: _______________________
Mailing Address Same as Physical Address ☐
PO Box: _______________ Rural Route Number: _________________ Unit/Suite/Building Number: __________
Street Number: _______________ Street Name: ________________ Street Type: ________________________
Street Direction: _______ City: ____________________________________________________________
Province/Territory: ____________________ Postal Code: ________________ Country: __________________
National Pollutant Release Inventory (NPRI) ID: _________________________________________________
North American Industry Classification System (NAICS) code: ________________________________________
Technical Contact
Name: ___________________________________________
Position/Job Title: ___________________________________
Mailing Address
PO Box: _______________ Rural Route Number: _________ Unit/Suite/Building Number: _________________
Street Number: ____________ Street Name: _______________________________ Street Type: ___________
Street Direction: _______ City: _____________________________________________________________
Province/Territory: ____________________ Postal Code: ________________ Country: __________________
Telephone Number: ____________________ Extension: ________ Fax Number: _______________________
Email: ______________________________________________________________________________
General Contact Same as Facility Technical Contact ☐
Name: ___________________________________
Position/Job Title: ___________________________
Mailing Address
PO Box: _______________ Rural Route Number: _________ Unit/Suite/Building Number: _________________
Street Number: ____________ Street Name: _______________________________ Street Type: ___________
Street Direction: _______ City: ____________________________________________________________
Province/Territory: ____________________ Postal Code: ________________ Country: __________________
Telephone Number: ____________________ Extension: ________ Fax Number: _______________________
Email: ______________________________________________________________________________
2.0 Use of Plans Prepared or Implemented for Another Purpose — No data is required for Part 2.0 of this Report.
3.0 Information on the Size of the Receiving Freshwater Body (other than the Great Lakes) — No data is required for Part 3.0 of this Report.
4.0 Information on Implementation of the Pollution Prevention (P2) Plan
Indicate the Implementation Year for which you are reporting: from (Year-Month-Day) to (Year-Month-Day).
All information provided in this Declaration will refer to this Implementation Year.
In Part 4.0, where indicated, use the following Basis of Estimate Codes to describe how each quantity reported in this part of the Declaration was determined:
- M1 Continuous Emission Monitoring Systems
- M2 Predictive Emission Monitoring
- M3 Source Testing
- C Mass Balance
- E1 Site-specific Emission Factor
- E2 Published Emission Factor
- O Engineering Estimates
- X Other (please specify)
4.1 On-site Uses
Did this facility use hydrazine on-site during the Implementation Year?
☐ Yes ☐ No
Use/Process (select all that apply)
☐ As a physical or chemical processing aid (e.g. boiler water chemistry control)
☐ Other
Total Quantity of all On-site
Uses for the Implementation Year (kg) |
Basis of Estimate Code |
---|---|
4.2 Releases to Receiving Water
Did this facility release hydrazine to receiving water during the Implementation Year?
☐ Yes ☐ No
If yes, report the quantity of all releases of hydrazine to receiving water.
Type of Releases to Waters | Quantity Released during the Implementation Year (kg) |
Basis of Estimate Code |
---|---|---|
a) Release to receiving water from all final discharge points | ||
b) Release to receiving water not through designated final discharge point (spills, leaks) | ||
TOTAL | n/a |
4.3 Release to On-site Water Treatment System
Did this facility release hydrazine to an on-site water treatment system during the Implementation Year?
☐ Yes ☐ No
If yes, report the quantity.
Release to on-site water treatment system |
Basis of Estimate Code |
---|---|
4.4 Off-Site Transfers for Disposal
Did this facility transfer hydrazine off-site for disposal in the Implementation Year?
☐ Yes ☐ No
If yes, report the quantity of all off-site transfers for disposal.
Type of Transfers for Disposal | Quantity Transferred for the Implementation Year (kg) |
Basis of Estimate Code | Facility Name and Address |
---|---|---|---|
a) Physical treatment | |||
b) Chemical treatment | |||
c) Biological treatment | |||
d) Incineration/thermal | |||
e) Containment | |||
f) Municipal Sewage Treatment Plant (MSTP) | |||
g) Underground injection | |||
h) Land treatment | |||
i) Other | |||
TOTAL | n/a | n/a |
4.5 Sampling and Analysis — Concentration of Hydrazine at Final Discharge Points
The table below must be completed separately for each Final Discharge Point.
Name of discharge point: ___________________________________
Name of receiving water body: _______________________________
Sample | Concentration of Hydrazine at the Final Discharge Point (µg/L) | Date of Sampling | Date of Laboratory Analysis | Laboratory Name, City and Telephone Number | Laboratory Accreditation Number |
---|---|---|---|---|---|
No. 1 | |||||
No. 2 | |||||
No. 3 | |||||
No. 4 | |||||
Average | n/a |
Comments
5.0 Action(s) Taken and Results Achieved
5.1 Action Taken
Parts 5.1.1 through 5.1.6 must be completed separately for each action taken in implementing the P2 plan, i.e. Part 5.1 will be completed as many times as there are actions taken to report.
5.1.1 Action Taken
What is the name of the action taken in implementing the Pollution Prevention Plan?
__________________________________________________________________________
What is the current status of this action?
☐ Completed
☐ Discontinued
If the action was "Discontinued," please provide the reason why.
For the action taken reported above, identify whether it represents a pollution prevention method(s) listed in Part 5.1.2 OR an environmental protection method(s) listed in Part 5.1.3.
5.1.2 Types of Pollution Prevention Methods
☐ Material or feedstock substitution
☐ Product design or reformulation
☐ Equipment or process modifications
☐ Spill and leak prevention
☐ On-site reuse, recycling or recovery
☐ Inventory management or purchasing techniques
☐ Good operating practices or training
☐ Other (please specify): _________________________
5.1.3 Types of Environmental Protection Methods
☐ Energy recovery
☐ Off-site recycling
☐ Incineration with energy recovery
☐ Waste treatment
☐ Pollution control
☐ Disposal
☐ Other (please specify): ___________________________
5.1.4 Changes Achieved: __________________________________________________
5.1.5 Baseline Elements Affected
☐ Quantity of on-site uses
☐ Releases to receiving water from all final discharge points
☐ Releases to receiving water not through designated final discharge point
☐ Releases to on-site water treatment system
☐ Quantity of off-site transfers for disposal
☐ Concentration in effluent at final discharge points
5.1.6 Completion Date of Action (YYYY-MM-DD): ___________________________________________
5.2 Total Results Achieved
Report the total changes achieved from ALL actions taken as a result of implementing the Pollution Prevention Plan described in Part 5.1 of the Declaration.
Type of Use/Release/Transfer | Total Anticipated Change Relative to the Preparation Year |
Total Anticipated Change Relative to the Preparation Year |
---|---|---|
On-site uses | ||
Releases to receiving water from all final discharge points | ||
Releases to receiving water not through designated final discharge points | ||
Releases to on-site water treatment system | ||
Off-site transfers for disposal | ||
Total |
5.3 Detailed Results Achieved Information
Report the total changes achieved from ALL actions taken as a result of implementing the Pollution Prevention Plan described in Part 5.1 of the Declaration.
Final Discharge Point | Total Change of the Concentration Achieved to Date Relative to the Preparation Year |
Total Change of the Concentration Achieved to Date Relative to the Preparation Year |
---|---|---|
1 | ||
2 | ||
3 | ||
4 | ||
5 | ||
6 | ||
7 | ||
Total | n/a | n/a |
6.0 Monitoring and Reporting
Describe the monitoring and reporting used to track progress in implementing the Pollution Prevention Plan.
7.0 Risk Management Objective
Do you meet the Risk Management Objective?
☐ Yes ☐ No
Describe how the elements of the Pollution Plan met the Risk Management Objective(s) for Hydrazine. If this Plan did not meet the Risk Management Objective, explain why.
8.0 Factors to Consider
Describe how the factors to consider set out in subsections 4(3) to 4(5) of the Notice were taken into account when preparing the Pollution Prevention Plan.
4(3) Priority to Pollution Prevention Activities
4(4) Coverage of Effluent Streams and their Identification
4(5)(a) Sampling Activities
4(5)(b) Analysis Activities
9.0 Certification
The information submitted in this Schedule will be made available to the public except for the
- general and technical contact information;
- parts that you requested confidentiality by clicking on the padlock icon on previous screens; and
- all information appearing on this page.
☐ I hereby certify that a Pollution Prevention Plan in respect of hydrazine has been prepared and is being implemented and that the information provided in this Declaration is true, accurate and complete.
Name: _________________________________________________
Title/Position: ___________________________________________
Email: _________________________________________________
Date: __________________________________________________
General Comments